RCKC Construction Updates for the Week of 3-24-25

(posted Mar 20, 2025)

FOR IMMEDIATE RELEASE
DATE: Thursday, March 20, 2025

Sign up for RCKC CONNECT to receive message alerts for road construction, road closures/detours, and general public news from the Road Commission of Kalamazoo County website at: www.kalamazoocountyroads.com

Kalamazoo, MI-            

In an effort to keep local drivers informed of the latest traffic and road maintenance operations by the Road Commission, we have provided the following update. For further information call 269-381-3171 or visit RCKC website www.kalamazoocountyroads.com.

“This information is made available to assist motorists in planning for construction delays,” Travis Bartholomew, Managing Director of the Road Commission said. “Motorists are reminded to be alert, slow down, stay informed, and be cautious when approaching a work zone. Remember, these projects signify progress in improving our infrastructure!”

Please note: This information is subject to change. Projects, road closures and timing can change from day to day, depending upon a number of factors, and traffic delays can develop in a matter of minutes due to weather conditions, emergency situations, etc.

Comstock Township

Road:  Sprinkle Road - I-94 BL to 581' north of Lake Street
Current Status:  Traffic control signage anticipated to be setup on 4/7/25.
Detour:  Lane closures are anticipated. No closure and detour of the roadway is anticipated. 
Project Information:  1.0 miles of construction of concrete shoulder and median, rumble strips, and paving.
Start Date:  April 7, 2025
End Date:  June 14, 2025

******************************************************************

Pavilion Township

Road: Q Avenue - 29th Street to 34th Street
Current Status: Tree removal and other clearing is scheduled to begin the week of March 17 and likely continue through the end of the month.
Detour: Q Avenue will be closed to through traffic during the project. The detour route is 29th Street, S Avenue, and 36th Street.
Project Information: This project includes tree clearing, crushing the existing asphalt to gravel-sized pieces and mixing with the existing gravel, widening of shoulder, paving, and drainage improvements, including some ditching. 
Start Date: March 17, 2025
End Date: August 4, 2025

******************************************************************

Richland Township

Road:  G Avenue - 28th Street to 38th Street (Richland / Ross Townships)
Current Status:  Traffic control signage anticipated to be setup on 4/14/25.
Detour:  G Avenue will be closed to through traffic at 28th Street during phase 1 of the project. The detour route is 32nd Street and Gull Road. 
Project Information:  Center left turn lane construction at 5 intersections along G Avenue at 28th Street, 31st Street, 32nd Street, 35th Street, and 38th Street. Project includes road widening for turn lanes, paving, and drainage improvements including some ditching. 
Start Date:  April 11, 2025
End Date:  August 31, 2025

###

 

For file attachment (PDF), click here